CenterPoint Energy Project

Project Scope: Transmission line upgrade in an existing right-of-way, with the installation of 100 foot tall concrete monopoles in a vertical configuration.

Challenges: Rough terrain, Dow Chemical Plant in the area placed restrictions on the project, residential area nearby and vibration sensitivity issues.

Completed the project on time, including setting the 8 foot diameter caissons in the ground, installing the rebar cage, pouring the concrete and setting the poles.

Drilling Equipment: Impact Hammer